| Project Description : |
Laying , Testing and Commissioning of Dadari -Bawana Pipeline Section and Associated Facilities (PART-A) for Vijaipur-Dadari-Bawana Pipeline Project of M/s.GAIL |
| Client : |
GAIL (India) Limited |
| Consultant : |
Engineers India Ltd., New Delhi |
| Project Duration : |
10 1/2 Month Mechanical + 1 Month Drying & Commissioning + 4 Month for Commissioning of C.P.System |
| Project Value : |
29.28 Crores (7.1 million US$) |
| Scope Of Work : |
- Residual Engineering
- Procurement
- Construction, Installation and Erection,
- All associated works
(Civil, Electrical, Instrumentations, Telecommunication & Cathodic Protection system)
- Pre-Commissioning and Commissioning
- Catodic Protection System
|
| Main Line : |
36” Dia – 40 Kms. |
| CP System : |
TCP & PCP |
| HDD Crossing : |
| Gang Canal - 36" Dia 300 Mtrs. (Approx) |
| Hindan River - 36" Dia 300 Mtrs. (Approx) |
| Water Pipeline - 36" Dia 250 Mtrs. (Approx) |
|